![]() |
Nene Valley RailwayCivil Engineering Group |
© 2005-2011 NVR |
CIVIL ENGINEERING - By Roger Manns
The work to finish the platform for opening formed part of our Civils Annual Work Week from 24 to 31 March. During March, the gravel surfacing was placed, and LNWR style fencing erected along the rear of the 7 coach platform. The fencing erection took longer than anticipated, some 6 days in total, but we saved a considerable sum by doing it ourselves rather than employing a contractor. Space is reserved at the west end of the platform for the LNWR replica station building, due to start in mid April, with completion planned in July. A building contract has recently been awarded to Graham Kirk Carpentry Ltd for the work, leaving internal fitting out by NVR before opening, probably in September. Many station signs have been made and erected and the view to the lake along the length of the platform is very attractive.
The footpath and its continuation to a tunnel viewing will be completed at a later date.
We also dropped ballast each side of Celta Road bridge on the Fletton Branch, and improved track drainage near London Road. Various other permanent way maintenance items were undertaken during Work Week. During January/February, hardwood point timbers were laid into 42 points and 41 catch switch had a replacement ½ switch and new hardwood timbers to try to ease the problem of rodding resistance on the long pull from Wansford signal box. We also spent 3 Saturdays on spot resleepering west of Castor, still leaving several outstanding. Don Crick has been busy with improvements to Wansford picnic site and Brian Dolby has been busy with various building maintenance jobs –level crossing gate, yard gate and door repairs, vandalism/break-in repairs, plumbing etc, as well as the bigger picture of assistance to David Head on the new Workshop building. Finally, work is progressing on our TASC Machine –more information next soon. |