NVR Logo - Click to return to front page

Nene Valley Railway

Civil Engineering Group

 

CIVIL ENGINEERING - By Roger Manns

© Bob RushbyFirst of all a tremendous thank you to everyone involved in the work to open Yarwell Junction Station on 7 April, all as planned.

The work to finish the platform for opening formed part of our Civils Annual Work Week from 24 to 31 March. During March, the gravel surfacing was placed, and LNWR style fencing erected along the rear of the 7 coach platform. The fencing erection took longer than anticipated, some 6 days in total, but we saved a considerable sum by doing it ourselves rather than employing a contractor.

Space is reserved at the west end of the platform for the LNWR replica station building, due to start in mid April, with completion planned in July. A building contract has recently been awarded to Graham Kirk Carpentry Ltd for the work, leaving internal fitting out by NVR before opening, probably in September.

Many station signs have been made and erected and the view to the lake along the length of the platform is very attractive.


© Ian WatsonThe TPO group are planning a second mailbag exchange apparatus point near the brick hut towards the tunnel portal, and the footpath route from the station will cross a deep dyke running in culvert under the railway. Now it just so happens that we have had in Ferry Meadows Yard a hardwood footbridge of 8.6 metre span that fits the bill. This is now in place over the dyke, and as an acknowledgement of all the hard work by Hannah in fund raising and co-ordinating the Yarwell Project, the bridge now has nameplates “Hannah's Bridge”.

The footpath and its continuation to a tunnel viewing will be completed at a later date.


© Mark AlthorpeIn the first 3 days of Civils Work Week we carried out essential track blanketing near Longueville Junction. This is located at two consecutive joints where wet beds and pumping have been giving us constant trouble for many years and I decided that remedial works were needed to resolve the problem once and for all.

© Mark AlthorpeThe location of the worksites in the cutting with a fence alongside meant careful pre-planning and logistical issues to get all the right materials in confined spaces. Track ballast and sand had to be bagged, loaded and offloaded and then moved to each worksite. Reach of the hired road/rail machine was critical to help move rails and concrete sleepers. But it all went according to plan, and track was kango packed, but I expect it will need further kangoing as traffic beds in the new ballast.

We also dropped ballast each side of Celta Road bridge on the Fletton Branch, and improved track drainage near London Road. Various other permanent way maintenance items were undertaken during Work Week.

During January/February, hardwood point timbers were laid into 42 points and 41 catch switch had a replacement ½ switch and new hardwood timbers to try to ease the problem of rodding resistance on the long pull from Wansford signal box. We also spent 3 Saturdays on spot resleepering west of Castor, still leaving several outstanding.

Don Crick has been busy with improvements to Wansford picnic site and Brian Dolby has been busy with various building maintenance jobs –level crossing gate, yard gate and door repairs, vandalism/break-in repairs, plumbing etc, as well as the bigger picture of assistance to David Head on the new Workshop building.

Finally, work is progressing on our TASC Machine –more information next soon.